推文作者对HBM产能需求进行估算:CXMT HBM产能约50-60K WPM,每片晶圆产出约2TB HBM3E,每个SuperCluster需75PB,对应3.75万片晶圆,约3周产出,认为当前产能不构成瓶颈。
I have no idea where "2M HBM stacks" comes from.
Now CXMT should be around 50-60K WPM for HBM. You get, what, 2TB HBM3E per wafer? 75PB needed per SuperCluster, 37.5 thousand wafers. 3 weeks of output.
I may be way way off but it doesn't look like a bottleneck. @zephyr_z9 https://t.co/gMe89abqrh
likes: 10 | retweets: 0 | replies: 1 | views: 16436